Capital Improvement Updates

Capital Improvement Updates2026-08-28T14:21:21-07:00
1211, 2026

Working Around the Weather

Adept, Able, and Accomodating As the rainy weather sets in, our dedicated crew from Pape and Sons, and our Coop Staff Representatives, are pivoting tasks to keep progress moving on our Capital Improvement. The large-scale excavation efforts we have seen on 238th and Burton Drive are simply not realistic when our region is experiencing even moderate rain. This may sound improbable to parents who have sat in all sorts of weather to watch [...]

611, 2026

New Main reaches the Loop & finds pieces of the past!

New pipe reaches the loop this week  On Monday Crews assisted by Nick Simmons and Morgan Berry reached 97th Ave SW; the junction with the Burton Loop system. Although there are more steps ahead before the construction is complete, this represents a major milestone in our Capital Improvement Project, and will allow us to focus on pressure testing the new pipes, and individual connections as the weather begins to preclude large scale excavation [...]

3010, 2026

2198 Yards This Season

Impressive yardage Our Contract Crew for the Capital Improvement Project from Pape and Sons has laid 2198.9 yards of new water pipe so far this season. Keep your eyes on them for the draft next year! In realistic terms: Pape and Sons has worked 41 days since the project began, which means we're averaging 53 yards per day, or about 160 ft.  Installation approaches 97th Ave SW Construction Management and Supervision [...]

2310, 2026

Construction Approaches 99th Ave SW

From 115th to 97th With just a little over a block to go, our USDA Capital Improvements have made a massive push from the West end of our system at 115th Ave SW, all the way down 238th, along 104th, past the fire department, across the highway, and East on Burton Drive, stopping just short of 99th this week, on the way to 97th Ave SW. Construction along Burton Drive East of the [...]

1610, 2026

New Water Main crosses the Highway

From the Fire Station to Harbor Mercantile The week of October 5th was monumental for the 2026 Capital Improvement Project, during which our contractors' excavated the path for the new 8" water main across The Highway along the South Side of Burton Drive . To date, this was the most visible and impactful portion of the construction efforts. Coming on the heels of the Judd Creek Bridge Closure, The Burton Water Cooperative Board, [...]

1809, 2026

September 18, 2026: USDA-Funded Project Weekly Update

Installation of new main line pipe continued this week from West to East along 238th, crossing 107th and reaching the intersection of 238th and 105th. Rocks in the path The unique geology of Vashon Island makes digging fairly consistent, until a very large boulder is encountered!   Crews encounter a big boulder This week our crews encountered a uniquely large boulder, and could not remove it without bringing a purpose made [...]