2808, 2026

August 28, 2026: USDA-Funded Project Weekly Update

Installation of new 8-inch main line pipe continued this week, with 1254 feet of pipe being installed West-to-East along SW 238th Street. Next week, the crew will continue installing pipe along SW 238th Street; the crew expects to reach 107th Avenue SW sometime next week. As of the date of this Post, once the crew reaches 107th, they plan to shift construction to the intersection of Vashon Highway and SW 228th Street and [...]

2108, 2026

August 21, 2026: USDA-Funded Project Weekly Update

Construction commenced this week, including installation of 500 feet of new 8-inch mainline pipe at the South end of 115th Avenue SW and the West end of SW 238th Street. The new pipe is being installed in the ground now but is not yet being put into service; individual service line connections will be made later this year after major segments of pipe installation are complete and the new pipe is pressure tested [...]

1408, 2026

August 14, 2026: USDA-Funded Construction to Begin

Construction Schedule On-site construction begins the week of Monday, August 17. The first day(s) are likely to be mobilization and setup only, with material and equipment arriving by ferry; though excavation may follow quickly. The first work will be the water main along SW 238th St from 115th Ave SW east to 107th Ave SW. Work will generally be Monday to Thursday from 7:00 am to 5:00 pm. Our contractor is still finalizing [...]