September 18, 2026: USDA-Funded Project Weekly Update
Installation of new main line pipe continued this week from West to East along 238th, crossing 107th and reaching the intersection of 238th and 105th. Rocks in the path The unique geology of Vashon Island makes digging fairly consistent, until a very large boulder is encountered! Crews encounter a big boulder This week our crews encountered a uniquely large boulder, and could not remove it without bringing a purpose made [...]
September 11, 2026: USDA-Funded Project Weekly Update
Installation of new 8-inch main line pipe continued this week from West to East along 238th. Over 2099ft. of new pipe have been laid along 238th since the beginning of the Capital Improvement Project. GPS data for new 8" pipe GPS Capture of new assets Throughout the construction our Co-op's Project Representatives - Nick Simmons and Morgan Berry - have been recording GPS Data for all of the materials being [...]
September 4, 2026: USDA-Funded Project Weekly Update
Installation of new 8-inch main line pipe continued this week from West to East along 238th, and crossed beneath 238th in preparation to connect the existing Co-Op tank on 238th. Additionally, crews conducted initial pressure testing, and sanitization of the existing 8” pipe that runs along 115th. This section of 8” pipe had been installed by Burton Water Company prior to the Co-Op and had never been utilized, so additional testing will be [...]
August 28, 2026: USDA-Funded Project Weekly Update
Installation of new 8-inch main line pipe continued this week, with 1254 feet of pipe being installed West-to-East along SW 238th Street. Next week, the crew will continue installing pipe along SW 238th Street; the crew expects to reach 107th Avenue SW sometime next week. As of the date of this Post, once the crew reaches 107th, they plan to shift construction to the intersection of Vashon Highway and SW 228th Street and [...]
August 21, 2026: USDA-Funded Project Weekly Update
Construction commenced this week, including installation of 500 feet of new 8-inch mainline pipe at the South end of 115th Avenue SW and the West end of SW 238th Street. The new pipe is being installed in the ground now but is not yet being put into service; individual service line connections will be made later this year after major segments of pipe installation are complete and the new pipe is pressure tested [...]
August 14, 2026: USDA-Funded Construction to Begin
Construction Schedule On-site construction begins the week of Monday, August 17. The first day(s) are likely to be mobilization and setup only, with material and equipment arriving by ferry; though excavation may follow quickly. The first work will be the water main along SW 238th St from 115th Ave SW east to 107th Ave SW. Work will generally be Monday to Thursday from 7:00 am to 5:00 pm. Our contractor is still finalizing [...]