Installation of new 8-inch main line pipe continued this week, with 1254 feet of pipe being installed West-to-East along SW 238th Street.

Next week, the crew will continue installing pipe along SW 238th Street; the crew expects to reach 107th Avenue SW sometime next week. As of the date of this Post, once the crew reaches 107th, they plan to shift construction to the intersection of Vashon Highway and SW 228th Street and begin installing new 6-inch pipe up the hill on 228th Westward toward 107th Avenue SW. 

Construction Management and Supervision

During all construction activity either Nick Simmons or Morgan Berry (part of our Operations crew) are required to be on site in order to observe, coordinate, and problem solve. Our engineers, Northwest Water Systems, will be on call at all times and on site as needed.

Traffic Management

Our contractor, Pape and Sons, will have flaggers at construction sites to direct traffic. Please assist by traveling slowly and following their direction. Some of our scope of work will overlap with the King County Judd Creek bridge closure, so please adjust your travel times accordingly.

Service Disruption

Every attempt will be made to minimize service disruptions. However, there is no way to do this work and have none. For planned disruptions, the Co-op will give 24 hours notice by email. Please make sure we have a current email address for whoever in your household you want to be the contact person. For unexpected disruptions, the Co-op will send an email communication as soon as practical. When possible, a Co-op representative will go to the impacted properties.

Emergency or Routine Contact Information

For general information about construction or for a non-urgent question, please contact the Co-op at info@burtonwater.org or 206-463-0005.

For an emergency or urgent matter, please contact our on-call personnel at 206-775-5667.

This short term inconvenience will provide long term operational security for our entire community. Thank you in advance for your understanding and cooperation during this critical investment in our water system infrastructure. Background information regarding this USDA-funded distribution pipe improvement project can be found on the Capital Improvement Plans page.